A $23.3 million project to rehabilitate the Fort Duquesne Bridge will resume this week after rain washed out much of the work planned for the weekend ...
Work will take place from 6 a.m. to noon, and all ramps to and from the bridge will remain open during the routine inspection by SAI Consulting Engineers ...
The ramp from the 10th Street Bypass to the outbound Fort Duquesne Bridge is to be closed starting Monday for repairs that will continue to keep it closed through Nov. 16 ...
Forecasters are predicting rain this weekend, so PennDOT is rescheduling demolition and repaving work on the ramps between the Fort Pitt Bridge and the upper, northbound deck of the Fort Duquesne Bridge ...
There may be intermittent single lane-closures on the 10th Street Bypass, Downtown, this week while crews work on ramps to the Fort Duquesne Bridge, state Department of Transportation officials said ...
Workers will close one southbound lane of Route 65 and the southbound ramp to the Fort Duquesne Bridge this weekend to remove monitoring equipment installed for the North Shore Connector project ...
A $26.2 million project to preserve the Fort Duquesne Bridge is a example of smart use of federal stimulus money to put people to work and save important infrastructure, Federal Highway Administrator Victor Mendez said Thursday ...